
Project Update: 01.08.2026
Reconstruction of the McKinley flushing channel is progressing on schedule with the ongoing installation of new steel sheet pile walls. Installation of the sheet pile tie-back system, rods, and anchors will begin soon, and demolition of the old concrete walls is nearing completion.




Project Update: 10.02.2025
The project contractor has begun mobilizing for the flushing channel reconstruction project. Construction is anticipated to begin mid-October.
Project Update 08.07.2025
Construction plans were completed, and the project was let for bids in late May 2025. A contractor has been selected and work on the reconstruction of the Flushing Channel isContinue reading

Project Update: 01.08.2026
Reconstruction of the McKinley flushing channel is progressing on schedule with the ongoing installation of new steel sheet pile walls. Installation of the sheet pile tie-back system, rods, and anchors will begin soon, and demolition of the old concrete walls is nearing completion.




Project Update: 10.02.2025
The project contractor has begun mobilizing for the flushing channel reconstruction project. Construction is anticipated to begin mid-October.
Project Update 08.07.2025
Construction plans were completed, and the project was let for bids in late May 2025. A contractor has been selected and work on the reconstruction of the Flushing Channel is scheduled to begin in Fall 2025. The project is anticipated to be completed in late spring/early summer of 2026.
Project Summary: Consultants completed an engineering study of the McKinley Flushing Channel, which is in a state of significant deterioration and in need of rehabilitation. The study provided development history, review of current conditions, results of various site investigations and recommendations for future rehabilitation of the channel walls. The flushing channel currently serves as a navigation way, provides dockage, and serves boating operations at the Milwaukee Yacht Club. Fishing also occurs, primarily at the headwall at the northern end of the channel.
Plans have been developed for reconstructing the channel walls, envisioned as primarily steel sheet pile with a concrete cap and railings. A portion of the historic channel walls will be reconstructed to tie into the headwall of the channel reconstructed by the Milwaukee Metropolitan Sewage District (MMSD) in 1996. A new walkway is proposed along the west side of the channel to provide a connection from Lincoln Memorial Drive to the McKinley Marina walkway system.
The public was previously invited to submit comments on the project. See presentation and/or video for project details.
Timeline: Construction is proposed for Fall 2025.
Proposed channel rehabilitation, west side looking southeast

Yes, all funding needs to be available before the project is bid. If there isn’t enough funding to cover the bid price, the project can’t be awarded.
Does all money need to be available before construction begins?