Scout Lake Parking Lot

Share Scout Lake Parking Lot on Facebook Share Scout Lake Parking Lot on Twitter Share Scout Lake Parking Lot on Linkedin Email Scout Lake Parking Lot link

Project Description

The Scout Lake Parking Lot has a condition score of 36/100, indicating an extremely deteriorated condition. Parks Operations staff have repeatedly repaired the lot with patching and stone, but due to the drainage conditions and slope of the site, the remedies wash out onto the adjoining pedestrian path creating a hazardous condition.

The pathway around the lake is also degraded and damaged, with a condition of 44/100. Scout Lake offers an accessible fishing pier reached by both the parking lot and the pathway. As a part of any reconstruction project, the scope would include drainage solutions, stormwater best management practices, lighting evaluation and replacement with Dark Skies, and energy-efficient solutions.

Property line and real estate ownership corrections will be completed as required throughout this project.

Pavement Condition Rating:

80 - 100 = Excellent
70 - 80 = Very good
50 - 70 = Good
30 - 50 = Poor
10 - 20 = Very Poor

0 - 10 = Failed

Timeline
The 2024 Capital Budget included an appropriation of $92,630 for the design work for Scout Lake’s Parking Lot and walkway. The 2024 Budget included a planned appropriation in 2026 for construction.

Please stay tuned for more updates as the project progresses.

Project Description

The Scout Lake Parking Lot has a condition score of 36/100, indicating an extremely deteriorated condition. Parks Operations staff have repeatedly repaired the lot with patching and stone, but due to the drainage conditions and slope of the site, the remedies wash out onto the adjoining pedestrian path creating a hazardous condition.

The pathway around the lake is also degraded and damaged, with a condition of 44/100. Scout Lake offers an accessible fishing pier reached by both the parking lot and the pathway. As a part of any reconstruction project, the scope would include drainage solutions, stormwater best management practices, lighting evaluation and replacement with Dark Skies, and energy-efficient solutions.

Property line and real estate ownership corrections will be completed as required throughout this project.

Pavement Condition Rating:

80 - 100 = Excellent
70 - 80 = Very good
50 - 70 = Good
30 - 50 = Poor
10 - 20 = Very Poor

0 - 10 = Failed

Timeline
The 2024 Capital Budget included an appropriation of $92,630 for the design work for Scout Lake’s Parking Lot and walkway. The 2024 Budget included a planned appropriation in 2026 for construction.

Please stay tuned for more updates as the project progresses.

Discussions: All (1) Open (1)
  • Let us know your thoughts on this project.

    6 months ago
    Share Let us know your thoughts on this project. on Facebook Share Let us know your thoughts on this project. on Twitter Share Let us know your thoughts on this project. on Linkedin Email Let us know your thoughts on this project. link

    You need to be signed in to add your comment.

    Your comments can help shape the future of your parks.

Page published: 31 Oct 2024, 11:18 AM