Warnimont Park Soil Remediation Project

Milwaukee County is addressing soil contamination at the former gun club site in Warnimont Park as required by the Wisconsin Department of Natural Resources (WDNR). The project includes environmental investigation and measures to prevent contaminated material from reaching nearby surface waters through erosion.

Originally funded in 2019, the project required additional funding due to expanded WDNR requirements, including further investigation of Lake Michigan sediments. Severe bluff erosion caused by high lake levels and storm activity also required a redesign of the remediation approach to improve safety, including the addition of a protective barrier fence. Updated construction costs also exceeded the original estimate.

The remediation work will be substantially completed in Fall 2026, with project closeout scheduled through Fall 2029 after the native seed is established. The total project budget is approximately $449,000, funded through Milwaukee County capital improvement appropriations.

Project Goals

  • Comply with state environmental regulations
  • Investigate and address contamination from historical gun club operations
  • Prevent public exposure to contaminated soils
  • Reduce erosion and protect Lake Michigan from contamination
  • Improve site safety through stabilization and protective barriers
  • Establish native habitat

The Trail is open, but seeding is still taking place.

Warnimont Park Soil Remediation Project

Milwaukee County is addressing soil contamination at the former gun club site in Warnimont Park as required by the Wisconsin Department of Natural Resources (WDNR). The project includes environmental investigation and measures to prevent contaminated material from reaching nearby surface waters through erosion.

Originally funded in 2019, the project required additional funding due to expanded WDNR requirements, including further investigation of Lake Michigan sediments. Severe bluff erosion caused by high lake levels and storm activity also required a redesign of the remediation approach to improve safety, including the addition of a protective barrier fence. Updated construction costs also exceeded the original estimate.

The remediation work will be substantially completed in Fall 2026, with project closeout scheduled through Fall 2029 after the native seed is established. The total project budget is approximately $449,000, funded through Milwaukee County capital improvement appropriations.

Project Goals

  • Comply with state environmental regulations
  • Investigate and address contamination from historical gun club operations
  • Prevent public exposure to contaminated soils
  • Reduce erosion and protect Lake Michigan from contamination
  • Improve site safety through stabilization and protective barriers
  • Establish native habitat

The Trail is open, but seeding is still taking place.

Discussions: All (1) Open (1)
  • Let us know your thoughts.

    10 days ago
    Share Let us know your thoughts. on Facebook Share Let us know your thoughts. on X (formerly Twitter) Share Let us know your thoughts. on Linkedin Email Let us know your thoughts. link

    Your comments can help shape the future of our parks. 

    Your comments can help shape the future of our parks. 

    You can use @ to tag somebody in the conversation

    Reply notification settings
    Email
    loader image
    Didn't receive confirmation?
    Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
    Submitting your comment
    Cancel
Page last updated: 13 Oct 2026, 10:23 AM